Ok, so you know we didn’t do the work today. Some guys from “Expressions in Flooring” came to build our customer shower pan today. They poured all the cement and made a slope from the edges to the drain. One of the guys asked if we were the ones who moved the drain or if a plumber did it, Zach told him we did it. This guy complemented us on a job well done! He said a lot of times they will come to do a job and the drain is crooked, etc. Yeah for us!! 🙂
So, after the cement was poured, the laid the waterproof sheeting and then more cement. (Zach could explain a more detailed version of how this works!)
Then they put in the corner piece for a seat and laid the tile for the floor. That was all they did – but it sure is A LOT!! We’re glad we ended up having them create the custom shower pan for us – because it would have taken us quite a bit longer to do it ourselves! And now it’s starting to look like a real shower! They got it all done today – so that means we can finish hanging hardibacker tomorrow afternoon… great, more work to do! haha! 🙂
Looks great though!!!